Qantas Freight Asphalt Rehabilitation

Milling, full-depth pavement repairs and asphalt paving near the main entry and exit gate of the Qantas Freight facility, run as night works.

Client
Solve Civil
Location
Mascot, NSW
Project size
Approximately 1,600 m²
Discipline
Asphalt

Scope of works

This project involved milling, full-depth pavement repairs, and asphalt paving for Stage 1 and Stage 2 areas near the main entry and exit gate at the Qantas Freight facility. The works were designed to restore the pavement’s structural integrity and provide a high-quality wearing surface capable of withstanding heavy operational traffic.

Works performed

Milling and waste removal

  • Completed 73 t of mill and fill works using a 2 m mill.
  • Milled the designated areas to a depth of 50 mm for wearing surface replacement.
  • In areas requiring full-depth pavement repair, milled to 100 mm, removing the deteriorated base material.

Base and wearing course installation

  • Patched full-depth repair zones with 100 mm of AC14HD hot-mix asphalt.
  • Supplied, laid and compacted 50 mm AC14HD hot-mix asphalt across all milled areas to create a uniform, durable wearing surface.

Outcome

The rehabilitated pavement areas now offer improved durability, structural stability and a smooth finish, enhancing both safety and operational efficiency at the Qantas facility. All works were completed to a high standard, on schedule, and with minimal disruption to daily operations.

On site

Photography from the job

Qantas Freight Asphalt Rehabilitation - work in progress
Qantas Freight Asphalt Rehabilitation - work in progress
Qantas Freight Asphalt Rehabilitation - work in progress
Qantas Freight Asphalt Rehabilitation - work in progress
Qantas Freight Asphalt Rehabilitation - work in progress
Qantas Freight Asphalt Rehabilitation - work in progress